George Bruce Library
HVAC and Fire Alarm Replacement
Replacement of HVAC and fire alarm systems and any associated work.
- Project Phase:
- Construction
- Projected Completion Date:
- 01-31-2024
- Capital Funding:
- $5,941,580.00
- Note:
- Funding is shared by multiple libraries.
Partial Interior/Exterior Rehabilitation, Roof Replacement
Exterior rehabilitation and roof replacement at landmarked branch. Work includes roof, roof drain, and leader replacement; window restoration or replacement as needed; refurbishment of the masonry facade; and restoration of damaged interior finishes.
- Project Phase:
- Design
- Projected Completion Date:
- 10-03-2025
- Capital Funding:
- $8,666,731.00